Wildcat Workzone – Progress Update – June 13th, 2025

To read historical facility updates and information, please visit the Wildcat Workzone page.

Track Replacement
We’re excited to share that the track surface has been milled and replaced this week! The new base layer will cure over the next month, after which the final running surface will be installed. During this curing period, the track remains open for student and community use—thank you for your patience and support!

Gym Exterior Painting
Progress continues on the gym! The exterior has been power-washed and the windows stripped to allow more natural light into the space. Weather permitting, exterior painting is scheduled to begin late next week.

New 7–12 Building Construction
The building site has been fully cleared, including the respectful removal and storage of all memorials. Major utility work is underway:

  • Electric: The MP building has been successfully reconnected to a new power feed.
  • Water & Sewer: Water service is temporarily off campus for the next 4–6 weeks as we install new water and sewage infrastructure.
  • Detention Pond: Land has been cleared to begin work on the new detention pond area.

MP Building
Abatement in the MP administrative area is now complete, and demolition is officially underway.

300 Building
Temporary interior walls are in place, and abatement has begun in the section scheduled for removal.

Site Overview

Front Circle

Detention Pond - Cherry Blossom entrance

Thank you for your continued partnership and patience as we invest in the future of Finneytown students!


Wishing you a safe and relaxing summer!

 

Grant Anderson
Director of Business Operations